Legal Analysis
Legal analysis from Dean's Law Dictionary will be displayed here.
Nature Of The Case
This section contains the nature of the case and procedural background.
Facts
Shinstine (D) was a general contractor that hired Ducolon (P) as a sub to do plumbing, heating, ventilation and air conditioning. D informed P that its bid was substantially lower than other bids and that it should review its bid. P did so and informed D that his bid was correct. D advised P of the low bid for a second time and P without checking his numbers increased his bid by 10%. P began work and was soon behind schedule and was eventually terminated for defective work and being behind schedule. P was replaced, and the work was completed for $16,268 half of which was attributed to completing of P's work and the other half to fixing P's defective work. P filed a materialman's lien and D counterclaimed. During trial, D argued that P could not recover an amount in excess of the $127,377. P argued that it was entitled to recover its actual cost of performance alleged to be $180,033 less progress payments of $89,746 made by D. The court ruled that D terminated the contract and also found that P materially breached the contract by delaying completion of the project for 30 days. The trial court awarded D $3,136.66 instead of the $90,326 requested. D and P appealed.
Issues
The legal issues presented in this case will be displayed here.
Holding & Decision
The court's holding and decision will be displayed here.
© 2007-2025 ABN Study Partner