Dynalectric Co., Inc. v. Clark And Sullivan Constructors, Inc.
255 P.3d 286 (2011)
Issues
The legal issues presented in this case will be displayed here.
Nature Of The Case
This section contains the nature of the case and procedural background.
Facts
UMC solicited bids for the Project. P, interested in serving as the general contractor for the Project, sought bids from subcontractors. D submitted a bid to P to perform the electrical work for the Project and repeatedly assured P of the accuracy of its bid. P incorporated D's bid into its bid to UMC for the general contract (Prime Contract). P was the low bidder, and UMC awarded it the Prime Contract. P notified D. D repudiated its obligations to P and refused to negotiate with P. P contracted with three replacement subcontractors to complete the electrical work for the Project. P then sued D in district court under various theories of liability, including breach of contract, promissory estoppel, and breach of the covenant of good faith and fair dealing. D countersued for, among other theories, breach of an implied contract, fraud, and violation of NRS 338.141. P got a judgment on its promissory estoppel claim. The district court awarded P $2,501,615 in damages, which represents the difference between D's bid ($7,808,983) and the amount P paid the three replacement contractors to complete the work ($10,310,598). D appealed.
Holding & Decision
The court's holding and decision will be displayed here.
Legal Analysis
Legal analysis from Dean's Law Dictionary will be displayed here.
© 2007-2025 ABN Study Partner