Hawa v. Moore
947 N.E.2d 421 (2011)
Legal Analysis
Legal analysis from Dean's Law Dictionary will be displayed here.
Nature Of The Case
This section contains the nature of the case and procedural background.
Facts
D bid on a job with P to provide a recycled concrete base for a parking area. D wanted $5000.00 down to start work - $5000.00 due when half of the area is done - Remaining balance is due upon 75% of work completed due to remaining material cost =$3500.00. P and D agreed to a contract price of $12,000 instead of the $13,500 bid. P wanted to see samples prepared with the material and to make sure it supported heavy traffic. In February 2009, P looked at the samples and handed D a $5000 check to begin work. D obtained two types of recycled concrete, each from a different supplier. From K-Enterprises, he bought $3000 and reserved $2000 of #2 rock. From IMI, he obtained #53 rock at no cost. D used J Stucki Trucking to transport the materials and some equipment to P's storage facility at a cost of $3795. The material was placed into nine piles. P complained that there was wire in the rocks and told D that he would not make the second payment because he was 'not happy.' D assured him that any wire would be separated from the rocks, and P allowed D to spread six of the nine piles. D asked about the second $5000 payment. P told him he needed to see eighty percent of the parking lot done before he would make the second payment. P told D that his bank would not advance him any more money for the second $5000 payment until it could inspect the work. D told P that he 'would meet at any convenient time with him and his banker.' D then moved the power rake blender to the front of the property, ready to meet the bank and complete the job, but the bank never visited the site. D left the power rake blender at the property for five days before he walked off the job. P filed a breach of contract claim in small claims court. Two months later in May 2009, D had more free #53 rock hauled to his own property, where he stockpiled it for use on P's project, at a transportation cost of $1500. D then filed a counterclaim demanding payment on the contract. D submitted a list of total costs for $10,495. This included the $1500 cost of hauling the free #53 rock to his own property. P denied that half of the area of the parking lot was done as required by the contract. D got a judgment of $4745. P appealed.
Issues
The legal issues presented in this case will be displayed here.
Holding & Decision
The court's holding and decision will be displayed here.
© 2007-2025 ABN Study Partner