Mccloskey & Co. v. Minweld Steel Co.
220 F.2d 101 (3d Cir. 1955)
Holding & Decision
The court's holding and decision will be displayed here.
Nature Of The Case
This section contains the nature of the case and procedural background.
Facts
McCloskey (P) made three contracts with Minweld (D) for D to furnish and erect the steel for two hospital buildings. The contract called for P to set up schedules for the delivery and erection of the steel. If D failed or refused to supply sufficient materials of proper quality, P would have the right to terminate on two days' notice. D received contract drawings and specifications for both buildings in May 1950. On June 8, 1950, P wrote D asking when it might 'expect delivery of the structural steel' for the buildings and 'also the time estimated to complete erection.' D submitted a scheduled estimate of expecting to begin delivery of the steel by September 1, and to complete erection approximately November 15. P wrote D threatening to terminate the contracts unless the latter gave unqualified assurances that it had effected definite arrangements for the procurement, fabrication, and delivery within thirty days. D replied that he had difficulty procuring the steel due to the outbreak of the Korean War. D requested help from P or the state to find steel. P treated this reply as a breach. P terminated the contract and hired another contractor who had no problem procuring steel. P sued D for anticipatory breach. P claims that by the last reply, read against the relevant facts, D gave notice of its positive intention not to perform its contracts and thereby violated same. D moved for dismissal after P's case was completed. D's motion was granted. P appealed.
Issues
The legal issues presented in this case will be displayed here.
Legal Analysis
Legal analysis from Dean's Law Dictionary will be displayed here.
© 2007-2025 ABN Study Partner