Solar Applications Engineering, Inc. v. T.A. Operating Corporation

327 S.W.3d 104 (2010)

Free access to 20,000 Casebriefs

Nature Of The Case

This section contains the nature of the case and procedural background.

Facts

P and D entered a contract to build a truck stop. The parties agreed on a construction schedule and P began work according to the schedule. D was required to provide monthly progress payments. When P believed the construction project ready for its intended use, that it is 'substantially complete,' it so notifies D and if D. agrees that the project is substantially complete, P issues a 'certificate of Substantial Completion' and attaches a list of items, referred to as the 'punch list,' to be completed or corrected before final payment. Upon written notice from P that the punch list is done and the project is complete, D conducts a final inspection with to identify any deficiencies, and P remedies those deficiencies. After P corrects the identified deficiencies, it may submit a 'final Application for Payment' that is accompanied by complete and legally effective releases or waivers of all lien rights ('lien-release affidavit'). Both parties agree that the project was substantially complete in August 2000. Disputes arose over the remaining items that needed to be completed before final payment. P then filed a lien against the project for $472,393, and subcontractors also filed liens against the property. D terminated P pursuant to the contract's 'for cause' termination provision contending that, among other things, P had failed to keep the project lien-free and failed to complete the punch list. D also notice P that it was asserting claims for $736,800.15 for D's failure to complete the construction project on time. The day after D terminated the contract, P provided an 'Application and Certificate for Payment' for $472,149. D refused to make payment, contending P had not complied with the lien-release provision by failing to submit a lien-release affidavit. D maintains that it has no obligation to make final payment on a building with outstanding construction liens. P sued for breach of contract under substantial performance for the unpaid balance of the contract, and D counterclaimed for alleged delays and defective work. The jury found for P awarding $392,000 in damages, which represented the balance due under the contract less an $ 8,000 offset to remedy all remaining 'punch list' defects and omissions found by the jury. D appealed and eventually, the court of appeals reversed and rendered judgment that P take nothing. The lien-release provision was a condition precedent and held that the doctrine of substantial performance did not excuse P's failure to provide a lien-release affidavit, and thus P forfeited final payment under the contract. P appealed.

Issues

The legal issues presented in this case will be displayed here.

Holding & Decision

The court's holding and decision will be displayed here.

Legal Analysis

Legal analysis from Dean's Law Dictionary will be displayed here.

© 2007-2025 ABN Study Partner

© 2025 Casebriefsco.com. All Rights Reserved.