Southwest Engineering Co. v. United States

341 F.2d 998, cert. denied 382 U.S. 819 (1965)

Free access to 20,000 Casebriefs

Holding & Decision

The court's holding and decision will be displayed here.

Nature Of The Case

This section contains the nature of the case and procedural background.

Facts

Southwest (P) entered into four contracts to construct radio facilities for the United States (D). Each of the contracts fixed a completion date and provided for liquidated damages on a per diem basis of $100 per day on one project and $50 per day on the other three. All four projects were finished late. The parties stipulated that even though late, D suffered no actual damages on any project. P sued D to recover holdbacks totaling $8,300. D moved for summary judgment, and it was granted. P appealed.