Wholesale Sand & Gravel, Inc. v. Decker

630 A.2d 710 (1993)

Free access to 20,000 Casebriefs

Facts

On June 13, Wholesale (P) agreed to perform work for Decker to install a gravel driveway. There were no time limitations, but the contract specified payment was to be made in 90 days. P started work and told D that the work should be completed in one week even though P believed it had 90 days. Difficulties in the work surfaced because the ground was too wet. P decided to wait for the ground to dry. D contacted P on July 12, and on July 19 to get the work finished. P responded that he would get right on it. D called on July 28 to terminate, and P promised to show up the next day. P did not appear, and D terminated the agreement. There was still 45 more days remaining. P sued, and judgment was entered for D; P's conduct constituted anticipatory repudiation. D appealed.

Nature Of The Case

This section contains the nature of the case and procedural background.

Issues

The legal issues presented in this case will be displayed here.

Holding & Decision

The court's holding and decision will be displayed here.

Legal Analysis

Legal analysis from Dean's Law Dictionary will be displayed here.

© 2007-2025 ABN Study Partner

© 2025 Casebriefsco.com. All Rights Reserved.