Carter v. Sherburne Corp.,

132 Vt. 88 (1974)

Free access to 20,000 Casebriefs

Nature Of The Case

This section contains the nature of the case and procedural background.

Facts

Four contracts were entered into between P and D wherein P was to perform construction work and be paid in weekly progress payments with 10 percent being held back until 10 days after acceptance. Eventually, D terminated the work by P. P did $52,571.25 in work and was paid $41,368.05 with holdback and $6,606.75 improperly taken by D. P sued D for payment and the trial court found that $4,747.25 was improperly taken by D and decreed that amount to P and in addition the court awarded P the $4,596.45 retained by D under the agreement. The court ruled that P substantially performed and that many of the contract delays were caused by D and that P was also entitled to quantum meruit upon work completed for free based on promises by D to procure more work for P. D appealed.

Issues

The legal issues presented in this case will be displayed here.

Holding & Decision

The court's holding and decision will be displayed here.

Legal Analysis

Legal analysis from Dean's Law Dictionary will be displayed here.

© 2007-2025 ABN Study Partner

© 2025 Casebriefsco.com. All Rights Reserved.