Fertico Belgium S.A. v. Phosphate Chemicals Export Ass'n
510 N.E.2d 334 (1987)
Nature Of The Case
This section contains the nature of the case and procedural background.
Facts
Fertico (P) entered into a contract with Phosphate (D) to purchase two separate shipments of 15,000 and 20,000 tons to be delivered not later than November 20th and 30th, 1978. D knew that P had a contract with Altawreed and that the timely execution of the contract was of great importance. P had secured a letter of credit with respect to the first shipment. D informed P that the first and second shipments would be late. P advised D that the breach of the time in the first shipment created huge problems and P canceled the second shipment because he needed the materials to be on time. P acquired title to the first shipment because he had no other choice. In an effort to avoid a second breach with Altawreed, P acquired 35,000 tons at a cost of $700,000 more. P then traveled to Iraq and renegotiated its contract with Altawreed. In return for a postponed delivery date and an additional payment of $20.50 per ton, P agreed to make direct inland delivery rather than delivery to Basra. P was left with 15,000 tons of late delivered goods that it was compelled to take because D had received payment from P's letter of credit. P sold the 15,000 tons at a profit of $454,000. P sued D for $1.25 million. The jury gave a verdict to P of $1.07 million. D appealed; the appellate court ordered that the increased transportation costs were not consequential damages, that the higher price paid by Altawreed was an expense saved as a consequence of D's breach, and that the damages must be reduced by the profit of the later resale of the 15,000 tons. P appealed.
Issues
The legal issues presented in this case will be displayed here.
Holding & Decision
The court's holding and decision will be displayed here.
Legal Analysis
Legal analysis from Dean's Law Dictionary will be displayed here.
© 2007-2025 ABN Study Partner