Hope's Architectural Products v. Lundy's Construction

781 F.Supp. 711 (1991)

Free access to 20,000 Casebriefs

Nature Of The Case

This section contains the nature of the case and procedural background.

Facts

Lundy (D) entered into a contract as general contractor for the construction of an addition to an elementary school. D's performance was guaranteed by a bond with Bank IV. Hope's (P) is a manufacturer of custom built windows and P contracted with D to manufacture 93 windows for the elementary school. The price was $55,000. The contract included a term relating to the time of delivery, but that was in dispute. Under P's interpretation, the windows were to be delivered in 12-14 weeks after receipt of the shop drawings (delivery no later than October 24, 1988). Production of the windows was delayed, and D threatened to withhold liquidated damages if the deadlines were not met. The windows were shipped on October 28 and delivery was anticipated on November 4. P then received a call from D and P claims that D threatened a back charge of $11,000 for late delivery of the windows. P requested assurances from D that no back charge would be assessed. D was unwilling to provide those assurances. P then suspended delivery by a letter dated November 2 until D provided assurances there would be no back charge. P then demanded prepayment from D before the windows would be delivered. D terminated the contract. P notified Bank IV and demanded payment on the work bond.

Issues

The legal issues presented in this case will be displayed here.

Holding & Decision

The court's holding and decision will be displayed here.

Legal Analysis

Legal analysis from Dean's Law Dictionary will be displayed here.

© 2007-2025 ABN Study Partner

© 2025 Casebriefsco.com. All Rights Reserved.